Guide to Understanding the Risk Assessment Matrix
Basic concepts, methodology, and application in occupational safety.
How does the 5x5 matrix work?
In occupational safety, a 5x5 matrix is most commonly used, which crosses two main components of risk:
- Likelihood (1-5): How likely it is that a hazardous event will occur (from "extremely rare" to "almost certain").
- Severity (1-5): How severe the injury or damage would be if the event occurs (from "negligible" to "fatal / catastrophic").
By multiplying these factors (L x S), we get the risk level (1-25), which tells us how urgently we need to act.
Risk Levels and Required Actions
Depending on the resulting number, risks are typically divided into several categories:
- Low Risk (1-4): Acceptable risk. No additional measures are required, but monitoring is needed.
- Medium Risk (5-12): It is necessary to plan and implement risk reduction measures within a reasonable timeframe.
- High Risk (15-25): Unacceptable risk! Work must be stopped immediately until measures to reduce the risk are implemented.
Hierarchy of Controls
When you identify a high risk, you must apply reduction measures in the following order: 1. Elimination (most effective), 2. Substitution (replacing the hazard with a safer one), 3. Engineering Controls (physical changes to the workplace), 4. Administrative Controls (procedures, training), and finally 5. Personal Protective Equipment (PPE) as the last line of defense.